Get ready for a SOC 2 audit
16 weeks · 5 phases · 32 tasks · 4 milestones · 5 risks
For a small company whose customers have started asking for a SOC 2 report and who has no compliance team. The weeks run from scoping and a gap assessment through writing policies and fixing controls to collecting evidence and handing over to an auditor. Adapt the scope to the services customers actually rely on, and decide early whether you're aiming for a Type I report first or going straight to a Type II observation period.
Makes it a program in your harbor, dated from today.
Milestones
- Week 4Scope set and auditor signed
- Week 8Policies approved
- Week 12Controls in place
- Week 16Fieldwork complete
The plan, phase by phase
1. Scope and choose an auditor
Weeks 1 to 4. Decide what the report covers and who will issue it.
- Week 1Name an owner for the auditOne person who chases evidence and talks to the auditor. It is a big part of their job for these months.
- Week 1List the systems and services in scopeStart from the product customers buy and the infrastructure, people and vendors it depends on.
- Week 2Pick the Trust Services Criteria to includeSecurity is required. Add availability, confidentiality, processing integrity or privacy only if customers ask for them.
- Week 2Decide between a Type I and a Type II reportType I looks at control design on one date. Type II tests that controls ran over an observation period, so it takes longer.
- Week 3Shortlist and interview audit firmsSOC 2 reports are issued by licensed CPA firms. Ask about their experience with companies your size, their timeline and their fee.
- Week 4Sign the engagement letter with the auditor
2. Gap assessment
Weeks 3 to 5. Find out which controls exist, which are informal and which are missing.
- Week 3Map current practices against the criteriaA spreadsheet with one row per control, its owner, and where the evidence would come from is enough.
- Week 4Run a formal risk assessment and record itList threats to the in-scope systems, rate them, and note the control that answers each.
- Week 4Inventory vendors that touch customer data
- Week 5Agree the list of gaps and who fixes each oneEvery gap gets an owner and a week. Unowned gaps are the ones still open at fieldwork.
3. Policies
Weeks 5 to 8. Write down the rules the company already follows, or should.
- Week 5Draft the information security policyKeep it to what you actually do. The auditor tests against what the policy says.
- Week 6Draft access control and offboarding policiesInclude how fast access is removed when someone leaves, and make sure you can meet it.
- Week 6Draft change management and code review policies
- Week 7Write the incident response plan
- Week 7Write the business continuity and backup plan
- Week 8Get policies approved and acknowledged by staffKeep the signed acknowledgments: they are evidence.
4. Fix the controls
Weeks 6 to 12. Close the gaps so each control runs the same way every time.
- Week 6Turn on multi-factor authentication everywhere in scope
- Week 8Run the first user access reviewCheck every account in every in-scope system against the staff list and remove what shouldn't be there.
- Week 8Require reviews before changes reach production
- Week 9Set up logging and alerting on production systemsDecide who reads the alerts and keep a record of what they did about them.
- Week 10Test a restore from backup and record the result
- Week 10Run security awareness training for all staff
- Week 11Collect security reports from key vendorsAsk for their own SOC 2 reports or equivalent and note how you reviewed them.
- Week 11Run an incident response tabletop exercise
- Week 12Arrange a penetration test and fix what it finds
5. Evidence and audit
Weeks 12 to 16. Gather proof that the controls run, then support the auditor.
- Week 12Build the evidence folder, one section per controlScreenshots, exports and tickets, each dated and labeled with the control it supports.
- Week 13Write the system description
- Week 14Do an internal readiness review against the evidence
- Week 14Fix anything the readiness review turned up
- Week 15Support auditor fieldwork and answer requestsAnswer within a day where you can. Slow replies are the usual reason fieldwork drags.
- Week 16Review the draft report and management response
- Week 16Schedule the recurring controls for the next year
What usually goes wrong
Scope grows too wide
Every extra system, criterion or team adds controls to build and evidence to collect.
What helps: Scope to the product customers are asking about and the infrastructure behind it. Add more in a later report.
Likelihood 3 of 5 · impact 4 of 5
Policies describe a company you aren't
Copied templates promise controls nobody runs, and the auditor tests against what is written.
What helps: Edit every template down to what you do now or will do by fieldwork. Delete what you won't do.
Likelihood 4 of 5 · impact 4 of 5
Evidence is collected at the last minute
Controls that ran months ago leave no trace if nobody saved the record at the time.
What helps: Save evidence as each control runs, into the folder for that control. Check the folder every two weeks.
Likelihood 4 of 5 · impact 3 of 5
The owner has no time for it
Audit work loses to product work every week unless someone is protected for it.
What helps: Agree up front how much of the owner's week this takes and what they stop doing. Review it at each milestone.
Likelihood 3 of 5 · impact 4 of 5
Engineering changes break controls mid-period
A new system or a skipped review during the observation period shows up as an exception.
What helps: Tell the engineering team which controls apply to them and add a check to the change process for new systems.
Likelihood 3 of 5 · impact 3 of 5
Using it
Copy what fits and cut what doesn’t: no real project matches a template. In Harbor the plan becomes a program with these milestones, one project holding every task with its due date, and these risks in the register, all yours until you hand them out. The first phase starts in To do and the rest wait in the backlog.
Open this in HarborMore plans
- Move offices10 weeks · 29 tasksA 10-week office move: plan and budget, prepare the new space, book movers and IT, update your address everywhere, then move and hand back the old office.
- Move to a new CRM10 weeks · 27 tasksA 10-week CRM migration: requirements and choice, field mapping, data cleanup and test imports, setup and training, then cutover and the first week of support.
- Roll out a new finance system20 weeks · 32 tasksA 20-week plan to replace a finance system: requirements, vendor choice, chart of accounts, data migration, parallel run and go-live.